Location: Sesquile, Columbia

  • Client

    Krones AG, Werk Steinecker

  • Final receiver:

    Central Cervecera De Columbia

  • Period of time:

    06.2018 – 03.2019

  • Value of the service [EUR]:

    1 230 000

  • Amount of manhour [h]:

    27 000

  • Quantity on site personel:

    8 – 40 pers

  • Scope of work:

    complete installation of brewhouse, malt transportation, cellar systems installation of cable trays • installation of power and control switchboards • electrical installation of malt production and transport process • electrical installation of brewhouse • electrical installation of fermentation process • electrical installation of filtration process • CIP electrical installations • installation of a storage room and beer storage • installation of fiber optic cables • PROFIBUS and PROFINET network installation • electrical and network measurements • participation in pre-commissioning and final commissioning after the installation is completed • participation in tests and optimization of production efficiency

Contact
+48 14 64 800 34

ul. Partyzantów 17B, 32-700 Bochnia, Polska